Supervision of works for the construction of four faecal sludge treatment plants and four landfills for Karongi and Rusizi Town (Design and Build) lot2
Key Project Features:
- One faecal sludge treatment plant in Rusizi,
- One faecal sludge treatment plant in Karongi,
- One landfill in Rusizi,
- One Land fill in Karongi,
- Disposition of solid waste in a way that causes minimum imp
Project Mission:
- Reviewing and approving survey works,
- Reviewing and approving engineering design,
- Updating of the environmental and social impact assessment( ESIA) And Carry Out Resettlement Action Plan,
- Supervision Of Works,
Deliverables:
- RAP report,
- ESIA report,
- Monthly report,
- Quarterly report,
- HSE report,
- Commissioning report,
- End of the project report.
Current Status: