• IBC GROUP House, Kn-5 rd, KK 83 Ave, kanombe-Kigali

project-image

Study and construction services for KAVUMU-MWANGE 30 KV


Key Project Features:

IBC Group has objective of carrying out Engineering, Procurement and construction Services for 30 KV- MV transmission line of about 4.5 Km from the Kavumu hydro power plant to the nearest national grid substation in Gicumbi district Northern Province

Project Mission:

Regarding the scope and requirements of the project, IBC was recruited to provide EPC services in a timely and successful implementation of KAVUMU Mwange transmission line. The main tasks assigned to IBC are as follow:

  1. Conduct a feasi

Deliverables:

Inception report, expropriation and environmental impact report, project progress report, minutes of meetings, design and construction report, Factory Acceptance Test (FAT) report, and Project completion report.

Current Status:

The project is 100% completed.